Skip to main content

// Case Study · Urban Bus Fleets · Hauts-de-France

DC fast charging for urban transit fleets

Why right-sizing beats oversizing: 5 × Lyra 80 kW deployed for a bus operator in northern France — and how smart specification delivered a stronger ROI.

Plug to the future

  • Client: Mona Energy
  • Location: Urban bus depot, Hauts-de-France region (northern France)
  • Challenge: Electrify the fleet with own DC infrastructure, optimising contracted grid capacity and making use of the 8+ hour overnight dwell time
  • Solution: 5 × Floox Lyra 80 kW, dual connector, 7-metre cables — expansion to 10 units already planned
  • Impact: Lower CAPEX vs. 120 kW alternative, reduced fixed grid costs, full charge with time to spare, and positioning as the regional benchmark for zero-emission public transport

The most valuable thing Floox brought to the table was convincing us that 80 kW was the right call. We initially assumed more power meant better performance, but the overnight dwell data made it crystal clear: the buses charge to 100% with time to spare, and our contracted grid costs are significantly lower. It is the smartest investment we have made in our electric transition.

— Fleet Operations Manager · Mona Energy · Hauts-de-France, France


Context: electrifying urban transit in northern France

Mona Energy is a French mobility and energy services operator active in the Hauts-de-France region — one of the most active urban transit corridors in northern France. A combination of the EU AFIR regulation, municipal decarbonisation targets and rising diesel costs accelerated the decision to install owned DC charging infrastructure at their main depot.

The site is well suited to overnight charging: buses return to the depot at the end of each service day and remain parked for over 8 hours before their next shift. That window is the foundation of the entire technical and commercial case for this project.

Site characteristics

  • Fleet-only depot with planned rotations and regular overnight dwell periods
  • Medium-size electric bus fleet with standard CCS2 charging ports
  • Guaranteed overnight charging window of over 8 hours
  • Variable distances between parking bays and charger positions — a key driver in cable length specification

Why act now?

  • AFIR Regulation: mandates own charging infrastructure at passenger fleet depots
  • Hauts-de-France regional decarbonisation incentives for sustainable mobility investment
  • Dependency on third-party public chargers: high and unpredictable cost per session
  • Growing demand for zero-emission transport contracts from regional municipalities

The challenge: getting the specification right from day one

The biggest risk in fleet electrification projects is not underspecifying — it is oversizing: paying for hardware capacity that will never be used and locking in a higher contracted grid tariff every single month. Mona Energy came to the initial conversation expecting 120 kW chargers, the option the market typically presents as the “safe” choice.

A joint technical analysis with the Floox team demonstrated that real operational data pointed in a different direction: with over 8 hours of overnight dwell time, an 80 kW charger — or even two buses sharing a dual-connector unit at 2 × 40 kW — delivered a full charge with time to spare. Oversizing was not just unnecessary — it was costly on two fronts simultaneously.

The hidden cost of oversizing

Installing 120 kW chargers in a depot with 8-hour dwell windows means 40–50% of installed capacity is never actually used. And that oversizing is not free — you pay for it twice. First in the unit price of the charger, which rises with power rating. Then every month, in the contracted grid capacity charge — the fixed line on the electricity bill whether the charger is running at full load or not.


The solution: Floox Lyra 80 kW — the intelligent choice

Following the real-use analysis, Floox specified 5 × Lyra 80 kW units with dual connectors and 7-metre cables. Choosing 80 kW over 120 kW was not a compromise — it was the technically correct specification for this site.

  • Model: Floox Lyra 80 kW
  • Configuration: Dual connector — 2 × 40 kW simultaneous or one bus at full 80 kW
  • Cable length: 7 metres, comfortably reaching every bus charging port across the depot layout
  • Units installed: 5 (full fleet coverage within the overnight window)
  • Planned expansion: 10 units in total to support fleet growth
  • Compatibility: CCS2 (Combo 2) — European standard for medium electric buses
  • Connectivity: OCPP — integrated with the Floox management platform

Why 7-metre cables?

Bus depot layouts are not uniform. Short cables leave some bays unreachable or force additional manoeuvring. At 7 metres, each Lyra unit reaches the charging port of any bus within its coverage radius — no repositioning of vehicles, no depot modifications required.

80 kW vs. 120 kW: the analysis that changed the decision

CriterionLyra 80 kW ✓ Selected120 kW alternative
Hardware unit costSignificantly lowerHigher price per unit
Contracted grid capacity requiredLower — fixed monthly network chargeHigher — fixed charge whether used or not
Match to overnight dwell window (8 h+)Full charge delivered with time to spare4–5 hours of installed capacity left idle
Real utilisation of installed powerHigh — capacity matched to actual useLow — 40–50% chronically underutilised
Total CAPEX (5 units)Lower initial investmentHigher investment with no operational benefit
ROIFaster payback — savings on two frontsSlower payback — double penalty

Implementation: zero downtime, built to scale

All installation phases were scheduled around the fleet’s service shifts, ensuring buses remained fully operational throughout the project. Floox coordinated directly with the local certified installer and Mona Energy’s technical team from day one, covering everything from engineering design to OCPP integration and staff training.

Installation process

  • Pre-engineering: depot layout analysis, distance mapping and installation point definition to maximise 7-metre cable coverage
  • Civil works: conduit routing and connections — no structural changes to the depot, no operational bays affected
  • Installation & commissioning: 5 Lyra units mounted, wired and configured; OCPP integration with the Floox platform and functional testing on live vehicles

Built to scale from day one

The electrical infrastructure and management backoffice were sized from the outset to support 10 chargers. The planned expansion — already agreed to meet fleet growth — will not require changes to the management platform or main switchboard. New units simply connect into the existing system. This future-proof approach was a decisive factor for Mona Energy.


Project economics: from scepticism to ROI

The economic case for right-sized overnight charging in public transport fleets is particularly strong. Savings materialise on two lines simultaneously: lower upfront investment and lower recurring network costs. Both contribute to a shorter payback and better long-term return.

5
Lyra 80 kW
units installed
10
Units in the
planned expansion
8 h+
Overnight dwell
window available
100%
Battery state at
start of every shift
7-meter
Cable — full
depot coverage

Break-even point

The dual cost reduction — lower CAPEX per unit versus 120 kW and lower contracted grid capacity month on month — significantly shortens the amortisation period. With systematic overnight charging across the full fleet, the return is robust and predictable from the very first month of operation. The argument is straightforward: you pay less to install and you pay less every month to run.

Cumulative savings (vs. public charging)

0€10k€20k€30k€

JulAugSepOctNovDecJanFeb

Upward trend as operations mature

Energy dispensed (MWh / month)

05 MWh10 MWh15 MWh

JulAugSepOctNovDecJanFeb

Stable volume across full overnight charging cycles

Charging sessions vs. Energy

03570
07.5 MWh15 MWh

JulAugSepOctNovDecJanFeb
SessionsEnergy

Regular high-capacity sessions — deep overnight charging pattern

Growing cumulative savings · stable and increasing energy volume · regular high-capacity sessions consistent with systematic overnight full-charge cycles.


Business impact: more than a charger

The installation has transformed Mona Energy’s operational model. The depot has evolved from a passive parking facility into a smart, autonomous energy infrastructure that guarantees full fleet availability every morning — with no dependency on third-party networks.

🔋
Fleet always ready

Every bus starts its shift at 100% charge — no reliance on third-party infrastructure or availability

💷
Dual savings

Lower upfront CAPEX and lower fixed monthly network costs — savings working on two fronts at once

📋
AFIR compliance

Own infrastructure, fully documented and auditable in real time via the Floox management platform

📈
Planned growth

Expansion to 10 units with no changes to platform or main switchboard

🏙️
Regional benchmark

Mona Energy positioned as the reference operator for zero-emission urban transit in Hauts-de-France


Results

  • Correct technical specification from the outset: 80 kW proven to be the optimal choice for 8-hour overnight dwell windows, with no performance compromise whatsoever
  • Reduced total CAPEX versus the 120 kW alternative, with lower contracted grid capacity and greater investment efficiency across the full fleet
  • 100% autonomous depot operation: the entire fleet charges every night with no dependency on third-party infrastructure or availability risks
  • AFIR regulatory compliance secured with own infrastructure — scalable and ready for the already-planned expansion to 10 units
  • Mona Energy consolidates its position as the reference fleet electrification operator in the Hauts-de-France region

Right-sizing from day one is the most profitable decision you can make.

With Floox Lyra, we help fleet operators electrify with the technically correct solution for their real operational profile — no oversizing, no performance compromise.

Talk to us about your fleet →